What the Planned Data Centre Near South Hetton Would Mean for East Durham

A US developer wants up to seven data halls between South Hetton, Murton and Easington Lane. What it is for, the case for and against, and what happens next.

KBY News Desk16 min read
Stunning aerial view of English countryside with fields, forests, and small village in black and white.

A US developer wants to build a large data centre campus on land between South Hetton, Murton and Easington Lane in east Durham. The company, Tract, calls it Durham Technology Park. It would have up to seven buildings of computer servers, with an electrical capacity of up to 500 megawatts. Tract’s first public consultation closed on Monday 23 November, and it expects to submit an outline planning application to Durham County Council in December.

Updated Sunday 29 November, 18:45 UK time: added map links, summary tables, a timeline and a glossary.

Nothing has been applied for yet, so nothing has been approved. Several details neighbours care about most have not been published. They include building heights, noise levels and how much water the site would use. Those gaps matter, because they decide what living next to it would be like.

#The plan at a glance

The key facts fit in one table. Every figure in it is the developer’s own estimate or a maximum, not a final design.

NameDurham Technology Park
DeveloperTract, based in Colorado, US
WhereLand between South Hetton, Murton and Easington Lane
BuildingsUp to seven data halls, a logistics building and an on-site substation
PowerUp to 500MW electrical capacity, through the new 400kV substation at Hawthorn Pit
Used forCloud computing and AI, Tract says; no operator named
Jobs claimed310 direct and 740 indirect once open; up to 1,500 construction jobs a year
CoolingNot yet chosen
StageInitial design; first consultation closed 23 November
Next stepOutline planning application to Durham County Council, expected in December

#Where would it be built?

The site lies between the three former mining villages, about 8 miles east of Durham City, according to Palatinate, the Durham University newspaper. An aerial image in the BBC’s report shows South Hetton Road running along the site’s southern edge. The road separates the land from Easington Lane and South Hetton, with Murton to the north.

Tract’s own consultation website sets out how traffic would reach it. Construction vehicles would come in from the B1285 to the north. Once open, the campus would use two new entrances on the B1285. A third entrance onto South Hetton Road would be for emergencies only. The new National Grid substation at Hawthorn Pit, which explains why Tract chose this spot, sits close by to the south east.

To see the area yourself, open it on OpenStreetMap or Google Maps. The map is centred between the three villages rather than on an exact boundary, because Tract has so far published only an illustrative masterplan. Look for the B1285 to the north, where the main entrances would be, and South Hetton Road along the southern edge.

#Who is behind it?

Tract is based in Colorado, and Review North reports that this would be its first development outside the United States. Palatinate reports that Tract has already built 14 data centres across six US states. Its business is preparing sites rather than running them. It assembles land, secures planning permission and arranges power before bringing in a data centre operator.

That model explains one of the odder facts about the plan. Nobody yet knows who would use the buildings. Tract told the BBC it “does not know at this time” who might operate the facility. The company says preparing land and power takes six to eight years, while operators typically plan only two or three years ahead. No investment value has been disclosed.

#What would it be used for?

A data centre is a building full of computer servers that store data and run online services. Everything from streaming and online banking to AI chatbots runs on servers in buildings like these. The servers produce a lot of heat, so cooling them takes much of the power and, depending on the method, water.

Tract’s website says the campus would “attract cloud computing and AI applications that require low-latency access to compute”. Its examples are medical imaging, industrial robotics, autonomous systems and AI-supported manufacturing. Low latency simply means a fast response, which is one reason firms like to have computing close to the customers they serve.

The plan arrives as the North East pitches itself as a centre for AI. Review North notes that the government’s North East AI Growth Zone is centred on Cambois and Cobalt Park. It reports that the Durham site’s formal relationship with that zone has not been established.

#How much power would it need?

Tract says the campus would need enough power for an electrical capacity of up to 500MW. Review North explains that this is a maximum, covering the computers and the systems that support them. It is not electricity already being used, and it does not mean the full supply has been secured.

The power would come through a new 400kV substation being built beside the existing one at Hawthorn Pit. That work is part of Eastern Green Link 1, a £2.5bn National Grid and SP Energy Networks project. The 196km link will carry up to two gigawatts between East Lothian in Scotland and County Durham. Construction began in 2025, and the link is expected to be working in 2029.

Tract says it would pay for the extra electricity, water and other utility work the campus needs. For scale, Review North compares it with QTS’s campus at Cambois in Northumberland. That scheme is designed for 720MW of computing capacity, with total demand reported at about 1.1GW. Review North warns the two sets of figures are measured differently.

Power worries came up at the consultation. Gordon Jenkins, 75, told the BBC: “We’re also told we don’t have enough infrastructure for electricity, and yet these are going to start sapping massive amounts of electricity.” In our reading, the campus would draw from the national transmission network through Hawthorn Pit, not the local lines that supply homes. The application’s technical detail should confirm that.

#How it compares with other North East data centres

Durham Technology Park is one of several large schemes in the region. Review North lists the main ones, and warns that their published figures are not always measured the same way. Computing capacity counts only the servers, while total demand also includes cooling.

SchemeWhereSizeStage
Durham Technology Park (Tract)Between South Hetton, Murton and Easington LaneUp to seven data halls, up to 500MW electrical capacityConsultation held; outline application expected in December
QTS Cambois, backed by BlackstoneFormer Blyth Power Station site, NorthumberlandUp to ten buildings, 720MW computing capacity, about 1.1GW total demandOutline permission; detailed approval for the first two buildings
Sembcorp Energy UK and Digital ReefWilton International, TeessideFirst phase up to 280MWPlanning permission granted on 29 October
Teesworks data centre campusTeesworks, TeessideUp to 462,419 square metresPlanning approval

#What about water?

The cooling method has not been chosen, and it is the biggest single factor in how much water the site would use. Tract’s website lists indirect evaporative cooling, air-only closed-loop systems, or a mix of both. It says it is working with Northumbrian Water, and that any upgrades to the water network would be funded by Tract.

In general terms, evaporative cooling uses water to carry heat away, while air-only systems use little water but more electricity. A Tract spokesperson told the BBC that closed-loop systems “use about as much water as an office complex” once running. Palatinate reports Tract saying no toxic chemicals are used in the data centre.

Residents have reason to ask. The BBC reports that a large house fire in the village left homes without water for several hours. The East Durham Action Group (EDAG) is also worried about the risk of contaminating the Permian Magnesian Limestone aquifer. It describes the aquifer as an important source of drinking water for the area.

#Noise, height and how it would look

Tract has not published building heights or noise figures. One Murton resident told the Local Democracy Reporting Service: “It’s going to be 30 metres”. That figure is the resident’s, not Tract’s, and we could not find it in Tract’s own material.

On noise, Palatinate reports Tract saying its data centres use measures such as sound barriers and insulated walls. It says a detailed noise impact assessment is being carried out. Data centres keep standby generators for power cuts. Tract told the BBC these “only run for a few hours a month”, and that other systems can sharply reduce their noise and emissions.

On looks, Tract’s website says the buildings will be sited and designed around key viewpoints, with materials and colours chosen to reduce their visibility. A landscape plan would add planting over time. Philip Dowell, 70, was not reassured. “We’ve been led down the garden path before,” he told the BBC. “They promise to do this and do that.”

#Traffic and footpaths

Roads were a common worry at the consultation. One resident described the road to the site to the Local Democracy Reporting Service: “It’s an old country road. It’s 60 miles an hour.” They feared extra junctions would make it worse. A six to eight-year build would also bring years of construction traffic, so the routes for heavy vehicles will matter.

Tract also promises new and better public footpaths around the site. Its website says it is working with Durham County Council to upgrade the Hawthorn-Ryhope Way. It also mentions nature trails, community woodland and green space.

#The case for it: jobs, money and training

Tract’s main argument is jobs. Review North reports its estimates: up to 1,500 direct construction jobs a year over a six-year build, and 1,470 more through suppliers. Once open, it says, the campus could employ 310 people directly, with another 740 jobs supported indirectly. The permanent roles would include electrical engineers, data centre technicians, network specialists, operations managers and security staff.

Tract also forecasts £68m a year in economic output and about £58.3m a year in business rates. Review North points out these are developer estimates, and the consultation material does not show the calculations. The BBC notes the same about the jobs figures. How much of the rates money stays in County Durham would depend on local government funding rules.

Tract says it will work with local colleges and employment agencies on training, from apprenticeships to degree-level roles. Palatinate reports it is committed to working with Durham County Council and Sunderland City Council on routes into local jobs. Interested in that kind of work? Start with our guide to how IT apprenticeships work in England. Our guide to the first IT jobs you can be hired into explains the entry roles.

On nature, Palatinate reports Tract committing to the legally required Biodiversity Net Gain plan. That means at least a 10% increase in biodiversity value, secured for at least 30 years. Local businessman Lee Blenkinsop, 58, summed up the cautious view. He told the BBC the plan could bring benefits if it created enough jobs, but added: “I’m not sure about the pollution and where the power’s coming from.”

#The case against: a village that feels surrounded

The strongest objection is about everything else being built nearby. The BBC reports that a solar farm was approved across the road from the site earlier this year. About three battery storage schemes are planned near the village, along with another solar farm paired with battery storage. EDAG says it is monitoring 15 planning applications in the area. “The central issue is cumulative impact,” the group said.

Gillian Rodgers, who chairs South Hetton Parish Council, said the plans came “completely out of the blue”. She told the BBC it was “just a further blow to us as a community”. She said the likelihood of being able to support or welcome it, given everything else the village faces, “is really low”.

Dr Brian Brown of EDAG, a Murton parish councillor, said people were “very angry” about the scale. He listed pressure on the grid, the cooling systems and the loss of green space around the villages. Others felt left out. Ed Morrow, 68, said his daughter exchanged contracts on a new-build home near the site in July. “We can’t believe that it was just at the end of October that people began to find out,” he said.

#The good and the bad, side by side

Set out together, the claims and the worries line up issue by issue. The left column is what Tract says. The right column is what residents, the parish council and campaigners have raised.

IssueWhat Tract says it would bringWhat worries people
Jobs and money310 direct permanent jobs, up to 1,500 construction jobs a year and about £58.3m a year in business ratesThe figures are the developer’s estimates, with no workings published
PowerA connection to a new national grid substation, with Tract paying for the extra infrastructureFears that the site will use huge amounts of electricity
WaterClosed-loop cooling using about as much water as an office complex, and Tract funding any upgradesThe cooling method is not chosen yet; worries about supply and the aquifer
NoiseSound barriers, insulated walls and a noise assessment under wayNo noise figures yet, including for standby generators
LandscapeNew planting, footpaths, an upgraded Hawthorn-Ryhope Way and at least a 10% biodiversity gainLoss of green space, and building heights not yet published
RoadsTwo new entrances on the B1285, with South Hetton Road for emergencies onlyA fast country road, more junctions and years of construction traffic
The wider areaTraining and apprenticeships with local collegesA village already facing solar and battery schemes, now with a data centre too

#Where it stands now

The project is at its initial design stage. Tract held two consultation events at the Robin Todd Community Centre in South Hetton, on Friday 6 November and Monday 9 November. Its website says the consultation period ended on 23 November. Gordon Jenkins described the consultation to the BBC as a “sales pitch”.

The next step is an outline planning application, which Tract expects to submit in December. Outline approval would settle whether a data centre campus is acceptable on the site in principle. The detailed layout and look of the buildings would need further approvals later. Tract’s website says the outline plans set maximum limits on size and output, and any final scheme could not exceed them.

Reports differ on timing. Review North describes a six-year build. Palatinate reports that Tract expects construction to take eight years from 2027, and the BBC says it could take up to eight years. Either way, this is a project for the 2030s.

The timeline so far, and what is expected next:

WhenWhat
2025Construction starts on Eastern Green Link 1, which includes the new Hawthorn Pit substation
End of October 2026Residents say they first heard about the plans
Tuesday 3 NovemberTract’s plans are reported in detail, including the 500MW figure
Friday 6 and Monday 9 NovemberConsultation events at the Robin Todd Community Centre, South Hetton
Monday 23 NovemberTract’s first consultation closes
December 2026Outline planning application expected
2027Construction could start, Palatinate reports
2029Eastern Green Link 1 expected to be working

#How to have your say

The formal chance to comment comes once the application is submitted. Tract’s website says all the technical information will then be available. It also says comments will be taken into account when the council decides. Our advice is to be ready for it now:

  • Watch Durham County Council’s planning website from December, searching for “Durham Technology Park” or the site’s address.
  • Tell your parish council and your county councillors what you think. The chair of South Hetton Parish Council and a Murton parish councillor have both spoken publicly about the plans.
  • Keep comments to planning matters: noise, traffic, water, landscape, wildlife and how the scheme adds to others nearby. These carry the most weight.
  • Read the noise, traffic and water assessments when they appear. They will hold the figures the consultation did not.

These are the questions we would want the application to answer, and you can put them to your councillors word for word:

  • “Which cooling method has been chosen, and how much water will the site use in a hot summer?”
  • “What noise level is predicted at the nearest homes, at night?”
  • “How tall will the tallest building be, and where will it stand?”
  • “How often will the generators be tested, and at what times?”
  • “Which roads will construction lorries use, and at what hours?”
  • “How many of the jobs will be guaranteed for local people, and how will that be measured?”

#Why the detail matters more than the headline figures

We think this plan is neither as good as the developer’s figures suggest nor yet the threat some residents fear. The truth depends on detail that has not been published. The reason for the site is real. A new substation on the national grid next door is exactly what data centre builders look for. That is why we expect interest in sites like this one to keep growing.

The weak points are just as clear. The job and business rates figures are the developer’s own, with no workings shown. There is no operator, so nobody can say which company would run it or what it would actually compute. Above all, the facts that decide life next door are still unknown. They are the cooling method, the noise at night and the height of the buildings.

In our view, the outline stage is the moment that counts most. It sets the maximum size the scheme can ever reach. Residents who wait for the detailed designs may find the big decisions have already been made. We would change our view if the application came with published water and noise figures and a binding commitment on local jobs. That is what a good neighbour would offer.

#The terms in this story

Planning and data centre jargon can make a story like this harder to follow. These are the terms that come up most:

  • Data hall: a large building, or part of one, filled with racks of computer servers.
  • Megawatt (MW): a million watts. The 500MW here is the most the campus could draw, not what it would use all the time.
  • 400kV substation: a site where the highest-voltage national power lines connect to the rest of the network.
  • Outline planning permission: a decision on whether a type of development is acceptable on a site in principle. The detailed design needs later approvals.
  • Evaporative and closed-loop cooling: evaporative systems use water to carry heat away, while closed-loop air systems recirculate the same coolant and use far less water.
  • Biodiversity Net Gain: the rule in England that most new developments must leave nature at least 10% better off, secured for 30 years.
  • Business rates: the property tax paid by businesses, which helps fund local councils.
  • Cumulative impact: the combined effect of several developments on one area, rather than each judged alone.

Evidence trail

Sources and verification

Primary documentation and external technical references used in this article.

  1. 01Tract: Durham Technology Park consultation websitedurhamtechparkinfo.co.uk
  2. 02Tract: Durham Technology Park, Benefitsdurhamtechparkinfo.co.uk
  3. 03Tract: Durham Technology Park, Environmental considerationsdurhamtechparkinfo.co.uk
  4. 04Tract: Durham Technology Park, Have your saydurhamtechparkinfo.co.uk
  5. 05Review North: US developer unveils plans for 500MW Durham Technology Park data centre, 3 November 2026reviewnorth.co.uk
  6. 06BBC News (via Yahoo): Data centre plan 'further blow', say campaigners, 7 November 2026yahoo.com
  7. 07BBC News, Local Democracy Reporting Service (via Yahoo): Data centre consultation 'a sales pitch', 11 November 2026yahoo.com
  8. 08The Northern Eco, Local Democracy Reporting Service: Noise and water supply fears over data centre plan, 11 November 2026thenortherneco.substack.com

About this page

Credited to

Dates

Published

Corrections

No corrections are listed for this page. Some review sweeps corrected pages without naming each one; those are in the corrections log.

Found this useful? Follow KBY for more like it.

Reader Interaction

Comments

Add a thoughtful note on What the Planned Data Centre Near South Hetton Would Mean for East Durham. Comments are checked for spam and held for moderation before appearing.